Tallinn, Paldiski mnt 201 korterelamu ehituse organiseerimise projekt

Laanemägi, Tanel (2015) Tallinn, Paldiski mnt 201 korterelamu ehituse organiseerimise projekt. [thesis] [en] A Construction Management Plan for an Apartment Building at Paldiski mnt 201, Tallinn.

[img]
Preview
PDF - Published Version
Download (1MB) | Preview
[img] HTML - Supplemental Material
Download (4MB)
[img]
Preview
PDF (lihtlitsents) - Supplemental Material
Download (118kB) | Preview
[img]
Preview
PDF - Supplemental Material
Download (1MB) | Preview

Abstract

Käesolev lõputöö on lahendatud Tallinnas, Paldiski mnt. 201 aadressil asuva kortermaja ehituse organiseerimise kohta. Töö koostamisel lähtus autor arhitektuursest ja konstruktiivsest projektist. Lisaks on kasutatud elektripaigaldise, veevarustuse ja kanalisatsiooni ning kütte ja ventilatsiooni projekte. Lähtudes standardist EVS 885:2005 kujunes koondeelarveks 2 321 332,4 €, millest 160 862,8 € moodustavad ehituse organiseerimise kulud. Ehituse organiseerimise kulud moodustavad koondeelarvest 6,93 %. Eelarve koostamisel on kasutatud EKE NORA andmebaasi ja tööde ajanorme on korrigeeritud vastavalt Ratu andmebaasile. Tõstetööde läbiviimiseks valis autor lähtudes elementide massist, tõstekaugusest ja -kõrgusest rataskraana Liebherr LTM 1080, mille hinnaks kujunes 28 220 €, alternatiivse tornkraana hinnaks oleks kujunenud 90 142 €. Ehitusprotsessi kestvus on 186 tööpäeva. Maksimaalne tööjõuvajadus on 68 töölist, keskmiselt on ehitusplatsil päevas 24 töölist. Käesolevas lõputöös on põhjalikumalt käsitletud nulltsükli ja tüüpkorruse montaažitöid. Nulltsükli tööde kestvuseks kujunes 38,4 päeva, iga päev on platsil 5 töölist. Tüüpkorruse montaažitööde kestvuseks kujunes 8,5 päeva, keskmine tööjõuvajadus on 5 töölist päevas. Tehnoloogiakaartide seletuskirjades on kirjeldatud tööprotsesse ja tööohutust, toodud välja töömahud ning joonestatud skeemid toetamaks seletuskirja. Tehnoloogiakaartide koostamine andis koostajale tööde tehnoloogiast uusi teadmisi. Töö koostamine andis kasulike teadmisi nulltsükli- ja montaažitööde kohta.

Abstract [en]

„A Construction Management Plan for an Apartment Building at Paldiski mnt 201, Tallinn.“ The objective of the thesis was to prepare a time schedule, a general plan of the construction site, to choose lifting mechanisms, to prepare technological maps for the zero-cycle and assembly of a standard storey. Based on the standard EVS 885:2005 “Construction cost classification" the final budget ended up with a sum € 2 321 332.4, of which € 160 862.8 are construction management costs. Unit prices and timelines are calculated with the help of EKE NORA data base. The construction management costs form 6.93% of the combined budget. Based on the weight, lifting distance and lifting height of the elements the author chose a wheel crane Liebherr LTM 1080 to perform lifting work. According to the calculations the price of the latter was € 28 220, the price of an alternative tower crane would have been € 90 142. The thesis includes a general plan of the construction site. The maximum number of construction site accommodation cabins needed at the site is 9 pieces. The length of temporary water mains is 38,6 metres and the length of temporary power lines is 229,3 metres. Based on the combined time schedule the duration of the construction process was calculated to be 186 working days. For calculating timelines the author used Eke Nora and Ratu data bases as references. The labour force requirement is above average from August till October. The maximum labour force requirement is 68 workers, in average there are 24 workers at the site per day. To prepare assembly and zero-cycle technology maps, the timelines stipulated in EKE NORA are adjusted based on Ratu data base. According to the calculations the duration of zero-cycle work is 38.4 days and the daily labour force requirement is 5 workers. Work shall be based on a zero-cycle technology map. The duration of the assembly work of a standard storey is 8.5 days and the daily labour force requirement is 5 workers. Work shall be performed pursuant to the standard storey assembly technology map and delivery schedule of reinforced elements.

Item Type: thesis
Advisor: Jüri Tamm
Subjects: Construction > Building Construction > Construction > Organization of construction
Divisions: Institute of Construction > Building Construction
Depositing User: Tanel Laanemägi
Date Deposited: 10 Jun 2015 07:57
Last Modified: 10 Jun 2015 07:57